The purpose of the proposed project is to generate hydropower and deliver it to China Southern Power Grid (CSPG). The proposed project involves the installation of 2 turbines, each of which has a rated output of 18MW, providing a total capacity of 36MW.

Project type

Renewable energy

Registry

Verra Registry

Project location

China

Certification

VCS (Verified Carbon Standard)
2017 - 2018
Available vintage
12 000 T/CO2
Available volumes
51 887 tCO2
Estimated Annual Emission Reductions
928
Project VCS ID

Certification(s):

SDG Goal(s):

No items found.

Project Image(s)

No items found.

Project description:

The implementation of the proposed project will achieve CO2 emission reduction by replacing electricity generated by fossil fuel-fired power plants.

‍

The proposed project involves the installation of 2 turbines, each of which has a rated output of 18MW, providing a total capacity of 36MW. The annual grid-connected output of the proposed project is estimated to be 143,6521MWh.

‍

The project will help reduce GHG emissions generated from the high-growth, coal-dominated power generation

‍

The proposed project will contribute to the sustainable development of the host country through the following aspects:

- Reducing the emission of other pollutants resulting from local coal-based power plants compared to a business-as-usual scenario;

- Alleviating local supply shortfalls of electricity (the CSPG is a net importer of electricity);

- Creating approximately 102 employment opportunities during the project operation and construction.

Download PDF →

See other projects

Contact Us

Got a question about our projects? Or you just want to talk with us. We are always up for a conversation.

📮 Thank you!

Your submission has been received. Our team will get back to you within the next days.
Oops! Something went wrong while submitting the form.